 Aug 1, 2004 10:59pm All the floors
have lights, except for the north stair-well.
|
 Aug 3, 2004 4:00pm Dalhousie lane
viewed from outside the meeting room (twist your head right as you
pan right).
|
 Aug 3, 2004 10:00pm The north
stairwell now has lights.
|
 Aug 3, 2004 The view from my office.
|
 Aug 4, 2004 That's what the new
furniture looks like.
|
 Aug 6, 2004 Signing-in at the
security-desk; with a bit of comedy relief on the right.
|
 Aug 7, 2004 The Gardiner Expressway
at 10am Saturday.
|
 Aug 7, 2004 Jim driving at 110km/hr!
|
 Aug 7, 2004 Check there's no police
on our tail.
|
 Aug 7, 2004 Coming up on Toronto.
|
 Aug 7, 2004 Nearly there.
|
 Aug 7, 2004 Pulling into the garage;
the moving truck is already there. No worries, as Nipin, Tu, Sergio
and Dan have got things under control before we arrive.
|
 Aug 7, 2004 IEEE student office gets new furniture (hi
Litifa).
|
 Aug 9, 2004 12:54pm One of the last
remaining desks to get loaded.
|
 Aug 9, 2004 2:19pm Then the chairs
and shelves begin their trip.
|
 Aug 9, 2004 6:00pm Since the freight
elevator is undergoing certification, the loading dock is off-limits
and we have to park on Church street and unload at the front
entrance.
|
 Aug 9, 2004 9:00pm Circuits lab being
set-up (you can tell it's night because it's dark outside the door).
|
 Aug 9, 2004 9:40pm The lab is set-up,
the equipment is locked and shrouded with drop-sheets to keep the
dust off.
|
 Aug 11, 2004 After an exhausting day,
Jim hopes that the movers will not notice him when they move the
furniture.
|
 Aug 11, 2004 Moving monitors as the
sun sets.
|
 Aug 11, 2004 Major cleaning of the
corridors.
|
 Aug 11, 2004 Carts used to transport
computers, monitors and other electronics.
|
 Aug 11, 2004 10:00pm What the...so
this is where all the garbage went.
|
 Aug 11, 2004 10:00pm Toronto at
night, viewed from the Balcony.
|
 Aug 12, 2004 The Front Office
counter.
|
 Aug 12, 2004 The Front Office
furniture awaits installation.
|
 Aug 12, 2004 10:00pm Setting-up the
equivalent of EPH 237— the most work-intensive lab (so far).
|
 Aug 12, 2004 11:00pm This is what
everything looks like, at the end of a week of 12-hour days.
|
 Aug 16, 2004 Installing the
floor-covering along the Balcony.
|
 Aug 16, 2004 9:00pm The exit signs
glow in the unfinished 3rd floor corridor. To receive an Occupany
Permit from the City, the building had to undergo a fire-inspection
and have working sprinklers, exit signs, corridors free of
obstruction, running water (cold), etc.
|
 Aug 19, 2004 Typical faculty office.
|
 Aug 17, 2004 11:00pm At the end of
the day, the radios re-charge. In a building with no working
telephones, and one which nearly spans an entire city block, radios
were the only means of communications.
|
 Aug 19, 2004 Sorting the network
patch- cables in the "shade".
|
 Aug 24, 2004 Front Office in EPH,
packed for moving. Yvonne is actually hiding behind the green box.
|
 Aug 24, 2004 New sidewalks are
poured.
|
 Aug 24, 2004 Unloading at the front
of the CCE (freight elevator inoperative (yet again!)) with a
make-shift bridge.
|
 Aug 24, 2004 If you're a fan of "101
Dalmations", drop-by the Computing Services offices.
|
 Aug 24, 2004 Catching-up on
Olympic coverage (with a discarded TV and a home-made antenna) while
waiting for the movers.
|
 Aug 24, 2004 2:00AM The old
server-room stripped of its contents. The primary RAID (top) and the
backup RAID are on the table on the left.
|
 Aug 27, 2004 The north sidewalk is
still under construction awaiting paving stones and decorative
bushes.
|
 Aug 27, 2004 The Atrium, viewed from
the entrance on the 3rd floor, is also under construction.
|
 Aug 28, 2004 Cleaning and polishing
before the students arrive on Monday, for registration.
|
 Aug 31, 2004 This is the
view from my office looking into the Computing Services office. The
reason everything is still in boxes is that I have no shelves, no
cabinets or desk drawers. So my office is used as a storage
room. Wait, there's more: I cannot connect my computer because the
electrical work is not finished (the lights are on only because 2
wires are shorted-together in the switchbox) and yes, that is a loop
of armoured cable hanging from the wall.
|
 Aug 31, 2004 Delivery of
paving stones on Gould.
|
 Aug 31, 2004 Paving stones
await installation; viewed from the 4th floor Front Office.
|

Aug 31, 2004
Mailboxes finally delivered...
|
.