May 10, 2004,
12:44pm Interesting blue sheen to the windows-- some sort of polarizer.
|

May 10, 2004, 8:00pm The
bricks begin to be laid on the steel frame at the south side.
|

May 10, 2004, 8:00pm The
elevator doors at the main entrance (a few bricks shy of a wall).
|

May 11, 2004,
12:44pm Installation of the gantry. Those metal bars installed on
the wall are for aesthetic gaps that follow the lines of the windows
on the east-side.
|

May 13, 2004, 2:00pm Packing
begins: the boxer (and 200 boxes).
|

May 12, 2004, 12:40pm Outside
masonry is half-way completed.
|

May 17, 2004,
12:40pm A close-up of a glass pane.
|

May 19, 2004, 12:40pm Outside
masonry completed (except for the bottom bit).
|

May 19, 2004,
12:44pm Installation of the flashing and siding on the north-west side.
|

May 24, 2004, 12:44pm Gantry
is removed. Lovely water-stains on the masonry along the top.
|

May 25, 2004,
12:45pm Finishing work being performed at the entrance.
|

May 25, 2004, 8:05pm The
loading dock on the south-east side along Dalhousie. Masonry still
needs finishing along the bottom (note visible insulation and
vapour-barrier). The window-lines along the east side continue
along the masonry (a nice touch).
|

May 25, 2004, 8:00pm Looking
south at the beautiful clouds reflected on the glass. The places
with missing panes are portals for transferring equipment to/from
the street using cranes mounted on flatbeds.
|

May 29, 2004,
12:44pm Scaffolding for installation of the lower portion
masonry at the south end.
|

May 29, 2004,
12:46pm Sealant and waterproofing for the outside of the sidewalk
along Church.
|