BASEMENT COMPLETED

Aug 5, 2003 8:05 PM
The strong-floor is finally poured.
|

Aug 5, 2003 8:05 PM
Looking East, construction of the foundation wall and main pillars inches northward.
|

Aug 28, 2003 12:35 PM Flatbed
truck delivers cement forms which the crane hoists on-site.
|

Aug 28, 2003 8:05
PM Foundation walls are completed and large girders are installed
on pillars, to support the first floor auditoriums.
|

Aug 28, 2003 8:05 PM At the
south end, the loading dock begins to take shape next to the freight
elevator.
|
Camera details: 3.2 megapixel Canon S30 SureShot with 3X
optical zoom; Av F2.8 - 8.0; Tv 1/1500 - 15 sec; ISO 50 - 800; manual
or automatic focus and light-metering capable.
Other Notes: Original photos have a resolution of 1600x1200
pixels. Panoramas are created using Adobe Photoshop to
"stitch-together" 2 or more images. Photos taken through the window
are Auto-Leveled then brightened.
Photography and Commentary: Luis
Fernandes.